Penalty for Breach and Damages in Commercial Contracts in Vietnam
How Vietnamese law treats contractual penalties and compensation for damages in commercial contracts, including the statutory penalty cap.
Table of contents
In the course of performing a commercial contract, it is hard to avoid situations in which one party fails to perform an obligation. When that happens, the two remedies discussed most often in Vietnam are the contractual penalty for breach and compensation for damages. Many businesses, including foreign companies contracting with Vietnamese partners, confuse the two or draft the relevant clauses loosely, and then find themselves at a disadvantage when a dispute arises.
This article explains how the two remedies differ, how the 8% cap on penalties under the Commercial Law 2005 works, the conditions for applying each remedy, whether they can be claimed together, and how to draft penalty and damages clauses that protect your position.
Penalty for breach and damages: the key differences
Both remedies arise when a contract is breached, but they are legally different in nature.
| Criterion | Penalty for breach | Compensation for damages |
|---|---|---|
| Nature | A remedy that the parties agree in advance | Compensation for loss that has actually occurred |
| Condition for applying | There must be an agreement in the contract | Applies even without an agreement, where loss has occurred |
| Must loss be proven? | No need to prove actual loss | Actual loss and the causal link to the breach must be proven |
| Limit | Up to 8% of the value of the breached part of the obligation (Commercial Law) | The value of actual, direct loss and the benefit the aggrieved party would otherwise have received |
Put simply, a penalty is a deterrent fixed in advance, while damages aim to compensate for the losses the aggrieved party has actually suffered.
The 8% penalty cap under Article 301 of the Commercial Law
Under Article 301 of the Commercial Law 2005, the penalty for breach of a contractual obligation, or the total penalty for several breaches, is agreed by the parties in the contract, but it must not exceed 8% of the value of the breached part of the contractual obligation. The only exception is the case of incorrect inspection results, which is governed by a separate rule.
Two points about the cap are often overlooked:
- The 8% is measured against the value of the part of the obligation that was breached, not necessarily against the total contract value.
- The cap applies only to commercial relationships governed by the Commercial Law. Other types of contract may be subject to different limits.
For other contracts, the position may differ:
- Civil Code 2015: the penalty is agreed by the parties and is not subject to a specific cap like the one in the Commercial Law, unless another relevant law provides otherwise.
- Construction Law: for works using public investment capital or state capital other than public investment, penalties for breach of contract are limited under the specific rules of the construction sector.
Before fixing a penalty rate, determine which law governs your contract, so that you do not agree a penalty above the applicable cap and lose the excess.
You may write a figure above 8% into a commercial contract, but the part that exceeds the statutory cap may not be accepted when the dispute is resolved. In practice, the enforceable penalty is limited to the statutory maximum.
Conditions for applying each remedy
Conditions for a penalty for breach
- The contract contains a clause in which the parties agreed on a penalty. Without such an agreement, no penalty can be imposed.
- A breach of a contractual obligation has actually occurred.
- The breaching party does not fall within one of the grounds for exemption from liability, for example force majeure or a breach caused entirely by the fault of the other party.
Conditions for compensation for damages
- There has been a breach of contract.
- Actual loss has occurred.
- The breach is the direct cause of the loss, meaning there is a causal link between the two.
The party claiming damages bears the burden of proving the breach, the actual loss and the causal link. It is also expected to take reasonable measures to mitigate its loss. For commercial contracts, damages can generally be claimed even if the contract contains no specific damages clause, as long as these elements are proven.
Can a penalty and damages be claimed at the same time?
This is one of the questions we are asked most often. Under the Commercial Law, the answer is yes, but it depends on whether the parties agreed a penalty clause:
- If the parties did not agree a penalty, the aggrieved party may only claim compensation for damages.
- If the parties did agree a penalty, the aggrieved party may apply both the penalty and the claim for damages at the same time.
This differs from the Civil Code 2015, under which applying a penalty and damages together depends on the specific agreement of the parties. Because the outcome turns on the governing law and on the wording of the penalty clause, both should be settled carefully when the contract is negotiated. Foreign parties used to other legal systems should not assume that the rules they know at home will apply in Vietnam.
How to draft robust penalty and damages clauses
To avoid disputes and protect your interests, the clauses should be drafted carefully and should cover the following points:
- Define the breaches that trigger a penalty, for example late delivery, delivery of goods that do not meet the agreed quality, or late payment.
- State the penalty rate and how it is calculated, for example as a percentage of the value of the breached part of the obligation, making sure it does not exceed the statutory cap.
- State expressly that remedies may be combined, confirming that the aggrieved party may claim both the penalty and damages.
- Set out how loss is proven and quantified, including the documents and records that will serve as the basis for calculating damages.
- Anticipate grounds for exemption from liability, such as force majeure or changes in law and policy.
- Choose the dispute resolution forum, either the courts or commercial arbitration.
The penalty clause is only one part of a well-built contract. Our article on eight essential clauses in a commercial contract and our contract review checklist cover the wider framework. If a dispute has already arisen, see our guides to commercial arbitration and commercial dispute litigation.
Frequently asked questions
What is the maximum contractual penalty in Vietnam?
For commercial contracts governed by the Commercial Law 2005, the maximum penalty is 8% of the value of the breached part of the contractual obligation under Article 301. For other types of contract, the limit may be different, for example under the Civil Code 2015 or the Construction Law.
Can a penalty be claimed if the contract has no penalty clause?
No. A penalty can only be applied when the parties have agreed on it in the contract. Without such an agreement, the aggrieved party can only claim compensation for its actual loss.
Can a party claim both a penalty and damages?
Under the Commercial Law, if the contract contains a penalty agreement, the aggrieved party may apply both the penalty and compensation for damages at the same time. Without a penalty clause, only damages are available.
Is a penalty agreement above 8% valid?
The part of the agreement that exceeds the statutory cap may not be accepted when the dispute is resolved, so the excess is generally not recoverable. It is safer to set the penalty within the limit allowed by the governing law.
Does a party need a damages clause to claim compensation?
For commercial contracts, damages can generally be claimed without a specific clause, provided the claimant proves the breach, the actual loss and the causal link between them. A clause describing how loss will be proven and quantified still makes the claim easier.
Does the claimant have to prove loss to receive a penalty?
No. A penalty does not require proof of actual loss; it is enough that a breach covered by the penalty clause has occurred and no ground for exemption applies. Damages, by contrast, require proof of actual loss and causation.
How LTV Law helps
LTV Law drafts and reviews penalty, damages and dispute resolution clauses so that they are enforceable under the law that governs your contract, and advises on claiming penalties and damages when disputes arise in Vietnam. See our contract drafting service and our commercial litigation service, or contact our team.
This article is for general information only and does not constitute legal advice.
Related insights
Trademark Registration in Vietnam for Foreign Companies (2026)
17 July 2026
Intellectual PropertyPatent Registration in Vietnam for Foreign Applicants (2026)
17 July 2026
Intellectual PropertyIndustrial Design Registration in Vietnam for Foreign Firms (2026)
16 July 2026
Intellectual PropertyEnforcing Intellectual Property Rights in Vietnam in 2026
16 July 2026
Need help protecting your rights in Vietnam?
LTV Law acts as your licensed local representative — from filing to enforcement.